Diagram of composition of the Foam Tank
Jan 02, 2024

Sealing inspection
First, the capsule should be given water-filled interior: Open the tank vent valve 6, the exhaust valve 8 capsule, close the valve 3 from the discharge valve 10 or irrigation fluid inlet 7 into the capsule filled with water, when the water discharge from the capsule 8 overflow valve, close the valve 8, valve 10 or valve 7; slowly open the inlet valve 4, a sandwich filled with water to the tank, when the water flows from the tank vent valve 6, close the valve 4, the valve 6.
Then slowly open the valve 4, to a pressurized tank filled with water, observe safety valve opening pressure gauge 5 and 2 (the valve opening pressure should be between 1.2-1.32MPa, otherwise, should be replaced).
When the pressure is stable at 1.2MPa, close the valve 4, pressure 15min, inspection equipment and piping systems all connections for leakage, paying particular attention to the lower part of the foam tank and drain valve 11 is connected to the flange surface leaks
If leakage, appropriate treatment should be done immediately.
Checked, when there is no leakage, open valve 6, the valve 8, valve 10, valve 11 and the water tank sandwich capsule emptying.
Check the factory before sealing do if the device holds a longer time or after maintenance checks should be sealed.
If you have any questions about foam tank, you can contact us through the following contact information
We will provide the fastest feedback
Pauline Lu
Head of sales Department "SANJING FIRE "
Phone/Skype/Whatsapp/Wechat: +86-13332933886
manager@sanjingfire.com